Project Overview
The bridges were designed to support 8 different piping schedules and maintenance platforms for regular servicing.
Works were completed on time despite a vertical cliff with a 15 m drop to water, restricted space and nearby high-voltage power lines.
Technical Details
- Concept and design by BridgePro
- Shop drawings and fabrication by BridgePro
- Designed to be disassembled allowing galvanising in Melbourne.
- Removal of old bridges and installation of new by BridgePro
Capabilities demonstrated
- Design management
- Complex steel ‘girder’ bridge