Project Overview
The City of Launceston commissioned the construction of a new pedestrian bridge, spanning the North Esk River between Seaport and Northbank, where an emerging upscale restaurant and park district was under development.
The City of Launceston sought an alternative to a standard rail truss: a bridge that met the technical requirements and suited the architecture of the precinct.
The council selected BridgePro’s design over competing cable-stayed and box-truss proposals on the basis of team, aesthetics and methodology.
The design departed from conventional solutions.
BridgePro used first-principles calculations, computer modelling, and prototype testing to ensure the new bridge conformed to Australian Standards and design specifications. The BridgePro design comprises three spans supported on two centre piers in a quad-pod pier arrangement. The significant design feature is the two arched 3D trusses running the length of the bridge on either side, providing the bridge’s structural rigidity. The truss-style bridge spans 120 metres and is four metres wide.
BridgePro is extremely proud to have achieved the result by collaborating with 100% Tasmanian companies.
Technical Details
Key features:
- Designed, fabricated and installed by Tasmanian-owned companies.
- Piles were driven from a jack-up barge to manage fast-changing tides and silty ground.
- 130 t of steel forms the 4 m-wide arched spans and an 8 m-wide landing platform, giving safe access for pedestrians and cyclists between Seaport and Northbank.
- The centre span clears a 1-in-2000-year flood and gives clearance for rowers on the North Esk, while staying low enough to preserve open views.
- The design includes a remotely controlled colour LED lighting system, with motion sensors that synchronise the lighting with pedestrian movement.
Capabilities demonstrated
- Complex foundations installed off floating plant (B4)
- Complex geometric / aesthetic shapes (B4)
- Significant fabricated steel superstructure (B4)
- Construction over water using floating cranes (B4)
- Consultant team coordination
- Design management
- Moderate to complex environmental management
- Complex community/ stakeholder interfaces and management (B4)