Project Overview
Bored piles and retaining walls that made room for two lanes in each direction.
BridgePro worked with Andrew Walter Constructions on the West Tamar Highway Duplication Project at Legana, between Freshwater Point Road and Acropolis Drive. The upgrade provides two lanes in each direction to improve safety and traffic flow for Legana and the wider West Tamar.
Our role was the retaining wall construction, including 178 bored foundation piles of 750 mm diameter, drilled with our almost 80-tonne Soilmec SR-75, and barrier installation along the new alignment.
The works were completed in April 2026.