Project Overview
Five strengthening contracts across four years, each between $200,000 and $1.8 million, delivered on live roads.
Between 2017 and 2020 BridgePro delivered a series of standalone bridge strengthening contracts for the Department of State Growth, designed by Pitt & Sherry, under AS 2124 construct-only terms. Together they demonstrate the range of the strengthening toolkit: carbon fibre laminates and near-surface-mounted rods, stainless steel dowels and plates, and composite precast deck replacement.
Inglis River Bridge (2020) – eight prestressed concrete beams strengthened with 1,600 linear metres of carbon fibre laminate, end anchorages and protective coatings, with GPR scanning of the deck before drilling and a crosshead crack repaired by low-viscosity epoxy injection.
Farm Creek Bridge (2018 to 2019) – over 2,500 linear metres of CFRP and more than 350 stainless steel anchor bars to strengthen the kerb-to-deck connection, delivered in phases on a live road from behind precast barriers.
Dunrobin Bridge (2018) – substructure strengthened with bonded stainless steel plates and the 74 m cast-in-situ deck replaced with 3.2 m precast panels on shear studs during weekend shutdowns.
Tarleton Street Overpass (2017) – over 400 linear metres of 16 mm near-surface-mounted carbon fibre rods installed into grooves over the piers, with asphalt removed and reinstated and traffic maintained throughout.
Stony Rise Road Overpass (2017) – over 1,400 linear metres of carbon fibre laminate on the prestressed bulb-T superstructure, with curing controlled by heating and minor concrete and crack repairs.