Project Overview
130 bored piles of 750 mm diameter toeing 4 m into Jurassic dolerite, in a single mobilisation.
The secant piled tank was formed with cased bored piling using segmental double-walled casing, with down-the-hole hammer gear to manage obstructions and integrity testing on 10 per cent of piles. Guide walls, a capping beam with pile break-back and excavation of the tank to RL -5.50 in fresh dolerite followed, with rock anchors installed to prevent flotation and dewatering to BridgePro’s treatment facility.
The methodology built on the approach proven at Davis Street, Smithton.
Key figures: 130 bored piles, 23 m tank diameter, 250-day programme.