Togari Bridge, Montagu

Replacement of a remote single-span bridge near Smithton with a 16 m long, 10.9 m wide structure on 4.5 m high cast in-situ concrete abutments.

Project Overview

Construction of a 16.0 m long, 10.9 m wide single-span bridge with 4.5 m high cast in-situ concrete abutments in a remote area of north-west Tasmania.

The works included formwork design, 50 tonnes of reinforcement, 400 m³ of concrete and 260 m² of site-specific formwork. BridgePro designed the formwork temporary works, which were independently proof checked.

The remote site called for a detailed logistics plan covering deliveries, storage and access routes. Reinforcement was delivered in batches against a clear placement plan, and the 400 m³ of concrete was poured in phases with on-site monitoring of curing.

Key figures: 16.0 m single span, 10.9 m wide, 50 t reinforcement, 400 m³ concrete. Design engineers: GHD.

Client:
Department of State Growth (head contractor Shaw Contracting)

Contract type:
Construct Only

Location: Montagu, near Smithton, Tasmania

Value: $1.63 million

Start:
December 2021

Completion:
April 2022

Related Projects

  • Union Bridge

    Union Bridge

    A new 72 m, three-span prestressed girder bridge over 10 m high for Meander Valley Council, founded on deep driven piles in karst ground.

  • TERHAP HDD Tie-In Sheet Pile Retention Structure

    TERHAP HDD Tie-In Sheet Pile Retention Structure

    Design, installation and removal of a temporary sheet piled retention structure for HDD tie-in connections on TasWater's rising main in Launceston.

  • Burnie Courts Complex Piling and Ground Anchors

    Burnie Courts Complex Piling and Ground Anchors

    Design and construct bored piles and ground anchors for the new Burnie Courts Complex, delivered for Fairbrother.