Mooring Dolphin at Berth 7 Burnie Port

The project involved the construction of a new mooring dolphin at the end of Berth 7 at TasPorts Burnie Facility. The completion of the dolphin permits the use of the wharf by much longer and larger ships, including cruise ships.

Mooring Dolphin at Berth 7 Burnie Port (2)

Project Overview

Cruise ships have become increasingly important to the Tasmanian economy delivering a significant economic injection into a regional economy. Newer cruise ships are increasing in size, meaning some of the newest were unable to visit. The new dolphin allows these larger cruise ships to visit Burnie.

Technical Details

Constructing a dolphin of this type in Burnie’s conditions was challenging.

Burnie, Tasmania, has significant tidal movement, up to 4m per day in fact (by comparison, Hobart is about 1.5m per day). This large tidal movement makes driving raking (on an angle) piles extremely difficult as the reference frame is constantly moving.

The way to overcome this tidal movement is through the use of a Jack Up Barge. That is a barge that has legs and lifts itself up off the water. Thereby eliminating the effect of the tide, and rough seas and minimising the effect of winds. All challenges present themselves at this location.

The jack-up barge’s relatively small size meant it could operate at the port without interfering with other port users, and its modular nature enabled it to be configured in a unique way which provided significant benefit to the construction

We used Down the Hole Hammer (DTH) Drilling in heavily raked piles to great effect. The use of raked piles meant traditional drill rigs could not be used. We developed a unique, single-length drill string over 30 m long to drill the piles. Into the drilled holes, we installed 30+m long pile anchors.

The dolphin was formed and poured in situ using over 70m3 of concrete. The formwork for the dolphin required significant falsework construction to support it on the heavily raked piles. In order to deliver the concrete to the dolphin, it had to be pumped along 120m of concrete pump line, which was ultimately controlled by the crane on the jack-up barge.

Capabilities demonstrated

  • Very heavy foundations, including complex rock sockets > 10m (B4)
  • Pile installation from floating equipment (B4)
  • Difficult installation conditions, including ‘grouting’ piles in wet conditions (B4)
  • Large/significant concrete pours (B4)
  • Construction over water using floating cranes (B4)
  • Construction ‘over’ navigable waterways (B4)

Client:
TasPorts

Contract type:
Construct Only, AS2124

Value:
$1.8 million

Start:
July 2016

Design:
BridgePro Engineering, Pitt & Sherry

Related Projects

  • Devil’s Gate refurbishment

    Devil’s Gate refurbishment

    Repair of erosion in the concrete-lined plunge pool below the Devil’s Gate Dam spillway for Hydro Tasmania, completed in 2017 ahead of the power station refurbishment.

  • Bridgewater Bridge Temporary Bridge Demolition

    Bridgewater Bridge Temporary Bridge Demolition

    Demolition of the temporary bridge built for the New Bridgewater Bridge project, including underwater pile extraction in the River Derwent and re-use of all steel bridge components.

  • Mersey Forest Road Bridges

    Mersey Forest Road Bridges

    New bridges on Mersey Forest Road for Sustainable Timber Tasmania, built with a BridgePro precast bridge system developed for hard-to-reach sites. Completed June 2023.