BridgePro Engineering is a leading Tasmanian contractor specialising in innovative and high-quality end-to-end solutions, from concept to construction.

The New Bridgewater Bridge

BridgePro was a key subcontractor to McConnell Dowell on the New Bridgewater Bridge, Tasmania’s largest ever transport infrastructure project, from initial tender through to execution. The new four-lane bridge carries a 1.2-kilometre deck across the River Derwent.

Project Overview

With a focus on local industry participation, the Tasmanian Department of State Growth awarded the design and construction of the new bridge to McConnell Dowell, with a commitment to engage local subcontractors throughout the project. BridgePro’s $80 million subcontract ran from October 2022 to 2025.

Our scope covered early constructability input and temporary works design and certification; offsite fabrication of the temporary bridge (200 prestressed decks and about 1,000 tonnes of superstructure steelwork) and its construction over 86 driven piles up to 42 m long, later removed and salvaged; and, on the permanent works, steel pier formwork, 34-tonne precast pile cap elements, pile reinforcing fabrication, all 42 in-situ piers and bored piling for the Black Snake Lane overpass.

The first pier is 12 m tall, holds 100 m³ of concrete and has a 34-tonne reinforcing cage. The piers get taller towards the navigation span, where they reach 15 m, before gradually shortening to 8 m at the Granton end. Each pier was poured as a single pour, with formwork designed by our engineering team to withstand the pressure of the concrete at that height and built by our boilermakers at BridgePro’s Latrobe site. More than 5,000 tonnes of reinforcing cage was fabricated at Latrobe.

Key figures: $80M subcontract, 42 in-situ piers up to 15 m tall, 86 piles 42 m long, 360 m temporary bridge rated for 400-tonne crane operations.

Like all of our projects, the New Bridgewater Bridge serves as a legacy for future generations and a testament to the skilled men and women who contributed to its design and construction.

BridgePro on the New Bridgewater Bridge, July 2023 (1 min 58 s)
Drone footage of construction on the New Bridgewater Bridge, November 2023 (4 min 54 s)

Client:
McConnell Dowell, for the Tasmanian Department of State Growth

Location:
Bridgewater, Tasmania

Contract type:
Subcontract to McConnell Dowell

Value:
$786 million (BridgePro subcontract $80 million)

Start:
October 2022

Completion:
2025

Award:
2026 CCF Tasmania Earth Award (project value over $150M)

Related Projects

  • Devonport 2 West Tug Berth Pontoon

    Devonport 2 West Tug Berth Pontoon

    Design and construct replacement of a small craft berth that had served the Port of Devonport for nearly 30 years, delivering a new 65 m tug berth and 30 m small craft pontoon for Tasmania’s freight and logistics network.

  • Tarraleah Canal No. 1 Remediation Works

    Tarraleah Canal No. 1 Remediation Works

    Remediation of Tarraleah Canal No. 1 for Hydro Tasmania from section T14 to the intake, delivered during a canal outage.

  • Mersey Forest Road Bridges

    Mersey Forest Road Bridges

    New bridges on Mersey Forest Road for Sustainable Timber Tasmania, built with a BridgePro precast bridge system developed for hard-to-reach sites. Completed June 2023.