Project Overview
A $216,000 design and construct piling package for the TasWater Capital Delivery Office.
BridgePro designed and certified the piles for a 50-year design life, then drove steel CHS piles up to 24 m with a 24 to 35 t excavator and impact hammer, splicing sections on site to reach founding depth. Capacity was verified by measured sets and the Hiley formula, and piles were cut to level, all within the operating treatment plant in a single mobilisation.
Key figures: Driven steel CHS piles up to 24 m.