130 piles into dolerite: the Macquarie Point pump station shaft

A 23 m diameter secant piled tank in Hobart, excavated to RL minus 5.5 in fresh dolerite, delivered in a single piling mobilisation.

For the TasWater Capital Delivery Office, through CPB Contractors and UGL Engineering, BridgePro built the secant piled tank for the Macquarie Point Sewage Pump Station: 130 bored piles of 750 mm diameter forming a 23 m diameter shaft, each toeing 4 m into Jurassic dolerite, with guide walls, a capping beam with pile break-back, and excavation of the tank to RL minus 5.50.

The piles were installed as cased bored piles using segmental double-walled casing, with down-the-hole hammer gear on standby for obstructions and pile integrity testing on 10 per cent of piles. Groundwater was pumped to BridgePro’s own treatment facility. Excavation proceeded in fresh dolerite, with rock anchors installed to prevent flotation of the finished structure, the same approach proven at Davis Street in Smithton.

The programme ran to about 250 days with the piling completed in one mobilisation. Read the project page.

Keep reading

More from BridgePro

  • What’s new on the BridgePro website

    Company

    5 November 2026

    What’s new on the BridgePro website

    The BridgePro website has been rebuilt around our 2026 capability: a project map, new Engineering & Design, Plant & Equipment, How We Deliver and Sustainability pages, and 24 completed project pages.

  • Inside BridgePro OS: how a START card gets read

    Safety

    5 November 2026

    Inside BridgePro OS: how a START card gets read

    A short walk through the field app, AI-reviewed START cards, SWMS checks and the live dashboards that earned BridgePro OS the 2026 CCF Tasmania Digital Technology Award.

  • 130 piles into dolerite: the Macquarie Point pump station shaft

    Projects

    4 November 2026

    130 piles into dolerite: the Macquarie Point pump station shaft

    Secant piled tank, capping beam and rock excavation for the TasWater Macquarie Point Sewage Pump Station, delivered through the CPB UGL joint venture.

  • Six rigs, 631 piles: foundations for a Launceston data centre

    Projects

    3 November 2026

    Six rigs, 631 piles: foundations for a Launceston data centre

    631 bored concrete piles of 900 mm diameter installed for a data centre development at St Leonards, Launceston, with multiple rigs working concurrently.