Devonport 2 West Tug Berth Pontoon wins the 2025 CCF Tasmania Earth Award

A $2.5 million design and construct project for TasPorts, replacing a small craft berth that had served the Port of Devonport for nearly 30 years.

The new 65 m tug berth and 30 m small craft pontoon give tugs, pilot boats and marine crews safe, all-tide berthing. The scope included demolition of the existing berth, a 55 m rock revetment using 1,400 tonnes of rock, and all steel components fabricated in-house at Latrobe.

Varying ground including basalt was addressed by fabricating a custom down-the-hole hammer to achieve pile accuracy and stability, with 35 m ground anchor tiebacks and a kick-up gangway designed for 3.5 m tides.

The project won the 2025 Civil Contractors Federation Tasmania Earth Award (Excellence in Civil Construction, $2M to $5M). Read the project page.

Keep reading

More from BridgePro

  • What’s new on the BridgePro website

    Company

    5 November 2026

    What’s new on the BridgePro website

    The BridgePro website has been rebuilt around our 2026 capability: a project map, new Engineering & Design, Plant & Equipment, How We Deliver and Sustainability pages, and 24 completed project pages.

  • Inside BridgePro OS: how a START card gets read

    Safety

    5 November 2026

    Inside BridgePro OS: how a START card gets read

    A short walk through the field app, AI-reviewed START cards, SWMS checks and the live dashboards that earned BridgePro OS the 2026 CCF Tasmania Digital Technology Award.

  • 130 piles into dolerite: the Macquarie Point pump station shaft

    Projects

    4 November 2026

    130 piles into dolerite: the Macquarie Point pump station shaft

    Secant piled tank, capping beam and rock excavation for the TasWater Macquarie Point Sewage Pump Station, delivered through the CPB UGL joint venture.

  • Six rigs, 631 piles: foundations for a Launceston data centre

    Projects

    3 November 2026

    Six rigs, 631 piles: foundations for a Launceston data centre

    631 bored concrete piles of 900 mm diameter installed for a data centre development at St Leonards, Launceston, with multiple rigs working concurrently.