Project Overview
A $2.28 million schedule of rates remediation package for Hydro Tasmania.
The works included 389.5 m of Sikaflex joint repairs, six Sikadur Combiflex joint repairs and 202 concrete patch repairs. Aluminium shutters were installed along the flume wall from T22 to the intake, around 50 m of coping blocks replaced, and 24 tie beams installed and tensioned. Voids beneath existing slabs were pressure grouted through 290 drilled holes before about 112.4 m³ of 40 MPa reinforced concrete overlays were placed at T14, T15, T18 and T19, with dust suppression and water management throughout.
Key figures: 389.5 m of joint repairs, 202 patch repairs, 112 m³ of overlays.