Project Overview
A $23 million subcontract over 18 months on site, with up to 90 staff.
The fixed shore ramp is a tightly curved and steeply graded structure with split grades across the deck. BridgePro worked with BMD and TT-Line to optimise the design, saving time and cost on a critical element of the project.
The works comprised 100 bored piles of 8 to 15 m socketed into hard rock and installed with a 25 m drilling rig, post-tensioned crossheads and Super T girders.
Key figures: $23M subcontract, 5 spans, 100 piles.