BridgePro Engineering is a leading Tasmanian contractor specialising in innovative and high-quality end-to-end solutions, from concept to construction.

Spirit of Tasmania Terminal 3 Fixed Shore Ramp

A five-span, four-lane fixed shore ramp for the new Spirit of Tasmania terminal in Devonport, constructed as a major subcontractor to BMD.

Project Overview

A $23 million subcontract over 18 months on site, with up to 90 staff.

The fixed shore ramp is a tightly curved and steeply graded structure with split grades across the deck. BridgePro worked with BMD and TT-Line to optimise the design, saving time and cost on a critical element of the project.

The works comprised 100 bored piles of 8 to 15 m socketed into hard rock and installed with a 25 m drilling rig, post-tensioned crossheads and Super T girders.

Key figures: $23M subcontract, 5 spans, 100 piles.

Client:
BMD / TT-Line

Status:
Completed; vessel berthing from August 2026

Location:
Port of Devonport

Value:
$23 million subcontract

Related Projects

  • Togari Bridge, Montagu

    Togari Bridge, Montagu

    Replacement of a remote single-span bridge near Smithton with a 16 m long, 10.9 m wide structure on 4.5 m high cast in-situ concrete abutments.

  • Latrobe Flood Mitigation Project

    Latrobe Flood Mitigation Project

    Bypass culvert, inlet structure and a rebuilt Cotton Street levee protecting Latrobe township from Kings Creek flooding, delivered as head contractor for Latrobe Council.

  • Devonport 2 West Tug Berth Pontoon

    Devonport 2 West Tug Berth Pontoon

    Design and construct replacement of a small craft berth that had served the Port of Devonport for nearly 30 years, delivering a new 65 m tug berth and 30 m small craft pontoon for Tasmania’s freight and logistics network.