We strengthened the bridge substructure using a series of bonded steel plates. We also replaced the bridge deck with a new, composite precast concrete deck system.
Project:
Dunrobin Bridge Strengethening
Client:
Department of State Growth
Contract Mechanism:
Construct only, AS2124
Key Personel:
Start Date:
February 2018
Date for Practical Completion:
May 2018
Design Engineers:
Pitt and Sherry
Budget:
$1.8m
Dunrobin Bridge Strengethening
We strengthened the bridge substructure using a series of bonded steel plates.
We also replaced the bridge deck with a new, composite precast concrete deck system. Added was an extra challenge, with the availability of the bridge on weekends only.
Technical Details
Installation of stainless steel plates to increase shear capacity of the hammer head piers. Plates bonded using Carbon Fibre techniques
Replacement of 74m of cast insitu non-composite concrete deck with full depth precast concrete panels in 3.2m lengths. The panels were connected to the girders with shear studs in grouted pockets.
The precast solution was an alternative to the designed precast/insitu concrete deck system. The alternative permitted the replacement within the allocated weekend shut down periods. The alternative was detailed by BridgePro in conjunction with the original design engineers.
Early in the bridge deck replacement, it was discovered that the bridge carried a significant fibre optic cable. This hiccup was managed smoothly and the cable subsequently relocated, supported and protected before returning to the completed structure.