BridgePro Engineering is a leading Tasmanian contractor specialising in innovative and high-quality end-to-end solutions, from concept to construction.

Bridgewater Bridge Temporary Bridge Demolition

Demolition of the temporary bridge built for the New Bridgewater Bridge project, including underwater pile extraction in the River Derwent and re-use of all steel bridge components.

Project Overview

Demolition of the temporary bridge constructed for the New Bridgewater Bridge project, working beneath the new bridge and over the River Derwent.

The works removed more than 4,000 tonnes of precast concrete deck panels, cut and extracted steel piles below water level, and dismantled girders and headstocks. All materials were transported off site by heavy haulage, and all steel bridge components were re-used to build the same temporary jetty on another project.

Grouted pin connections between deck planks and headstocks were precision cored. 191 deck panels and 78 girders were lifted out, 28 headstocks and 16 headstock extensions were dismantled, and specialist divers cut and extracted 72 steel piles at depths of 1 to 10 m using Broco cutting lances.

Working within the tight spacing of the new bridge piers called for a telescopic crawler crane, with a barge-mounted excavator removing pile offcuts. Environmental controls included marine mammal observation, silt curtains and strict water quality and sediment controls next to a conservation area.

Key figures: More than 4,000 t of precast deck panels removed, 191 deck panels, 78 girders, 72 steel piles extracted underwater.

Client:
McConnell Dowell

Contract type:
Construct Only

Location: Bridgewater, Tasmania

Value: $3.45 million

Start:
June 2025

Completion:
August 2025

Related Projects

  • Glenfern Road Bridge Replacement

    Glenfern Road Bridge Replacement

    Design and construct replacement of the Glenfern Road bridge for Derwent Valley Council, with a precast dual lane bridge built for improved flood capacity.

  • Burnie Port P6 Portainer Crane Controlled Collapse

    Burnie Port P6 Portainer Crane Controlled Collapse

    Controlled collapse of a decommissioned 680-tonne, 90 m high post-Panamax container crane at the Port of Burnie, stabilised by strand cable and cut remotely.

  • Togari Bridge, Montagu

    Togari Bridge, Montagu

    Replacement of a remote single-span bridge near Smithton with a 16 m long, 10.9 m wide structure on 4.5 m high cast in-situ concrete abutments.