86 CFA piles for the new LGH multi-storey car park
23 September 2026
BridgePro has completed the pile foundations for the new multi-storey car park at Launceston General Hospital, designed and built for Vos Construction.
Between February and September 2026, the team designed and installed 86 piles using the continuous flight auger (CFA) method. Our Soilmec rig recorded the depth, auger torque and concrete profile of every pile. The crew also fabricated and installed the reinforcement cages, then formed, reinforced and poured the pile caps and capping beam starter bars.
Stiff clays slowed auger penetration, so multiple extraction and re-entry cycles were managed under full-time supervision. When the design changed during delivery, BridgePro engineers issued revised design memos and certification so the builder could keep working without delay.
Low-strain integrity testing by Tasman Geotechnics was reviewed by our engineers against the rig and site records, giving the builder a single, complete quality record for the foundations. Read the project page.
Keep reading