BridgePro Engineering is a leading Tasmanian contractor specialising in innovative and high-quality end-to-end solutions, from concept to construction.

Port of Stanley Recreational Pontoon

A new floating pontoon with four berths at the historic Port of Stanley, plus remediation of about 50 m of sheet pile wall at Fishermans Dock.

Project Overview

A $1.5 million design and construct project for TasPorts with a 20-year design life.

BridgePro optimised the provided design to improve amenity and reduce construction risk, replacing about 50 m of sheet pile wall at Fishermans Dock with rock revetment and installing piles that allow a future increase from four to six berths.

Key figures: $1.5M contract value, 4 berths (6 future), 20-year design life.

Client:
TasPorts

Location:
Port of Stanley, Tasmania

Contract type:
Design and Construct

Value:
$1.5 million

Related Projects

  • Union Bridge

    Union Bridge

    A new 72 m, three-span prestressed girder bridge over 10 m high for Meander Valley Council, founded on deep driven piles in karst ground.

  • Rubicon River Bridge

    Rubicon River Bridge

    A new bridge over the Rubicon River on Smith and Others Road, Sassafras, replacing a single-lane timber structure for Latrobe Council. Completed October 2025.

  • Northern Geotechnical Drilling Campaign

    Northern Geotechnical Drilling Campaign

    BridgePro's jack-up barge provided a stable over-water platform for TasPorts' geotechnical drilling campaign at the Ports of Burnie and Stanley.