Union Bridge

The project involved the construction of a new 72m long, three-span prestressed girder bridge over 10m high.

Union Bridge

The project involved the construction of a new 72m long, three span prestressed girder bridge over 10m high.

Technical Details

  • 3 span bridge, dual lane
  • 72m long and over 10m high
  • Driven steel piles up to 70m long, precast concrete pier/ abutment, prestressed girders, cast insitu deck
  • Complex foundations into a karst (cave) system requiring a mid-construction design change to double the number of piles.
  • Installation using a 50t crawler crane on a barge along with erection gantries
  • Approach roadworks including cuts into a 10m high embankment and significant fill

Relevance to B3, R2 Prequalification Categories

  • Complex foundations involving deep piling
  • Pile installation from floating equipment (B4)
  • Cast insitu composite deck
  • Construction over water using floating cranes and erection gantries (B4)
  • Large / significant concrete pours (B4)
  • Significant earthworks including structural fill and rock protection

Project:
Union Bridge

Client:
Meander Valley Council

Contract Mechanism:
Design and Construct AS4902

Key Personel:

Start Date:
August 2016

Date for Practical Completion:
December 2017

Design Engineers:
BridgePro Engineering, CSE Tasmania

Budget:
$2.5 million